W10.0_Ahmed Al Azizi_ Effective Project Closure for Installation of Oil Transfer Pumps Project


  1. Problem Definition.

As a part from Field Development Program (FDP) it recommends introducing to upgrade the oil shipping facility. In this project two Oil transfer pumps to be installed in B station to increase the shipping capacity from 20,000 ppd to 50,000 ppd. In the below table a summary of project activities:

 

Table 1

Table 1 Project activities summary

 

As this project get completed a project closure to be performed. Wrap up the project and make sure the project team learns from what transpired. Get a true evaluation of the project results by the end user (operation team), other stakeholders, including project team members.

 

  1. Identify the Feasible Alternative.

Project closure includes:

  1. Contract closure.
  2. Administrative closure.

 

 

  1. Development of the Outcome for Alternative.

Contract closure includes the following activities and procedures:

Verification activities to be carried out to validate that contract terms and conditions have been met. This included the delivery and completion of the following activities by singing the completion certificates and delivery note from construction team.

Table 2

Table 2 Project activities summary and Contract closure

 

 

Administrative closure includes the following activities:

a. Collects project records.

d. Analyzes project success or failure through a workshop or comprehensive report.

c. Archives project information for future use.

 

  1. Selection of Criteria.

In the below figure schematic overview of Project Closure for Installation of Oil Transfer Pumps Project:

Figure 1
Figure 1 schematic overview of Project Closure

  1. Analysis and Comparison of the Alternative.

The process of managing all the little things that crop up at the end of a project that must be done before declaring the project successfully completed.

  1. Performance Monitoring and the Post Evaluation of Result.

The following procedure has been approved in the project charter:

Figure 2

Figure 2 Punch list Management process

Finally, as post evaluation step, prepare final technical reports to evaluate project performance and Summarize learning points. After that, conduct final review with management and keep project historical files and place in archive.

 

References:

  1. London Development Agency. (2005). The “How To” Guide to Project Succession or Closure. Retrieved from  http://www.networkforeurope.eu/files/File/downloads/HowToProjectSuccession.pdf
  2. Kevin F, Genny Edwards. (2011). 10 Tips for a Smooth Project Closure Process. Retrieved from http://www.brighthubpm.com/monitoring-projects/105533-ten-tips-for-a-smooth-project-closure-process/
  3. Engineering Dept., Daleel Petroleum (2012). Project Closure Report Installation of Oil Transfer Pumps Project.

 

Advertisements

One thought on “W10.0_Ahmed Al Azizi_ Effective Project Closure for Installation of Oil Transfer Pumps Project

  1. EXCELLENT, Ahmed!!!! Doing EXACTLY what I am looking to see you do. Taking the tools and techniques you are learning about and applying them in your real life projects…..

    Doesn’t get any better than this……

    Keep up the great work and PLEASE help your team members who are struggling with this assignment.

    BR,
    Dr. PDG, Jakarta

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s