W5_SuleimanAljabri_ The Schedule Leveling


 

  1. Problem Definition

One of the most important considerations of project planning is the scheduling of a project at the right level, at the right time – and that can be challenging. Executive-level and senior-level management scheduling have different needs and goals than stage- or phase-level scheduling, which may require more detailed planning.

2. Identify the Feasible Alternative

While there are differing views on the criteria that apply to summary- and detailed-level scheduling, it is generally understood that a coordinated approach is best. For example, Jelen’s position is that there is no universal agreement on the number of schedule levels or their format, while others take a progression elaboration approach to developing coordinating schedules across various levels of a project.

Figure.1: Gantt Chart

 

 

 

3. Development of the Outcome for Alternative

Developing a common work schedule framework from the onset allows for easier level schedule development as a project progresses. Of course, details will continue to be added to each level as activities are confirmed and processes are firmed-up.

Recent theories take a different approach to traditional level scheduling, especially regarding the details and information included in each level.

AACE International’s Recommended Practice No. 37 (RP 37), Chartered Institute of Building (CIOB Guide) and the Guide to the Forensic Scheduling Body of Knowledge Part I (FSBOK Guide) each bring new ideas into the project planning and scheduling field. But the main concept of establishing a common detailed framework for a project is universal.

 

Figure.2: The Team Activities List.

 

 

 

  1. Selection of Criteria

By using a combination of RP 37 and the CIOB Guide suggestions, you can implement a progressive elaboration approach. This approach is based on the idea that it’s impractical to plan a working schedule (with all of its details) at the onset on a project, since the schedule’s density will increase as more information and details become available and are confirmed.

Additionally, the FSBOK Guide introduces a multi-level schedule hierarchy. This helps ensure logical summary-level and detailed-level scheduling for mega- and major contracts through the creation of a foundation schedule. This five-level approach divides each level’s criteria into two categories: general intent and format, and scheduling objective. With this subdivision of criteria, each level is able to include all of the general details and information about the project and keep the team on the same page.

 

Figure.3: The Gantt Chart in Excel Sheet

  1. Analysis of the Alternative.

FSBOK’s multi-level hierarchy divides the scheduling into five levels:

  • Level 1: Graphical snapshot of driving summary activities and logic for executive and senior managers.
  • Level 2: Establish the driving critical path and near-critical path to contract, and key milestones for senior managers, including the project manager.
  • Level 3: Detail needed for construction management, staging deliveries and project control for construction manager and scheduling staff.
  • Level 4: Working schedule that supports Level 3 sequences for area supervision.
  • Level 5: Look-ahead schedule for crew foremen and supervision.

.

  1. Selection of the Preferred Alternative.

Although all of the new approaches agree that a common framework should be developed, they disagree on a method for addressing schedule density or granularity through the progression of the project. CIOB advocates increasing density of downstream activities, whereas FSBOK promotes holding to a uniform schedule granularity. Each approach has its advantages, and one may work better for certain projects and schedules than another, so it’s wise to be flexible and use alternative methods as needed.

  1. 7. Performance Monitoring and the Post Evaluation of Result.

Regardless of the approach taken, it’s important to keep all levels on the same page, making sure they are connecting with the overall schedule. To that end, the new approaches suggest using a coding structure to ensure horizontal and vertical integration throughout the project.

Approaches to project scheduling and planning continue to evolve and change, and it’s helpful to incorporate new ideas into your planning. But it’s also critical to remember that while each project and project team works differently, it’s vital to keep everyone on the same track through the duration of the project.

  1. References
  1. Jodi Sorensen (2013, July). How to Create a Gantt Chart in Excel Retrieved June 29, 2014, from http://www.smartsheet.com/blog/gantt-chart-excel?page=27
  2. Chart Director (2008, December). Simple Gantt Chart. Retrieved June 29, 2014, from  http://www.qrb-bw.de/pdf_pool/pythondemo/cdpydoc/gantt.htm

projectsmart. (2013, August). How to Create a Gantt Chart Using Microsoft Excel. Retrieved June 14, 2014, from http://www.projectsmart.co.uk/creating-a-gantt-chart-using-excel.php

Advertisements

One thought on “W5_SuleimanAljabri_ The Schedule Leveling

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s